Pedestrian Bridge over the Lerez River
Pontevedra, España
Typologie Pedestrian Bridges
Date Juillet, 1997
Maîtrise d'ouvrage Xunta de Galicia
Constructeur OCP construcciones. Operaciones de giro Lastra Ibérica. ACS
The pedestrian footbridge over the River Lérez comprises a lower deck arch with a span of 82,50 m and a rise of 13,40 m. Both deck and arch are steel structures. The arch is made up of a pipe of 1,00 m diameter. The deck which is 4,00 m wide and 0,80 m deep has a lens-shaped cross section.

The footbridge was built parallel to the river on one riverside. Once it was finished, the bridge ends were placed on two turning tables: one on shore and the other one off shore on a boat. The footbridge was first turned by the movement of the boat and then longitudinally shifted, holding the off shore bridge end with a crane and fixing the on shore one on a bed of sliding Teflon bearings which allowed its longitudinal launching.
Pro
© Diego Xuan
The pedestrian footbridge over the River Lérez comprises a lower deck arch with a span of 82,50 m and a rise of 13,40 m. Both deck and arch are steel structures. The arch is made up of a pipe of 1,00 m diameter. The deck which is 4,00 m wide and 0,80 m deep has a lens-shaped cross section.

The footbridge was built parallel to the river on one riverside. Once it was finished, the bridge ends were placed on two turning tables: one on shore and the other one off shore on a boat. The footbridge was first turned by the movement of the boat and then longitudinally shifted, holding the off shore bridge end with a crane and fixing the on shore one on a bed of sliding Teflon bearings which allowed its longitudinal launching.
© Diego Xuan
Pedestrian Bridge over the Lerez River
Pontevedra, España
Typologie Pedestrian Bridges
Date Juillet, 1997
Maîtrise d'ouvrage Xunta de Galicia
Constructeur OCP construcciones. Operaciones de giro Lastra Ibérica. ACS
Mission Detailed design and construction support
The pedestrian footbridge over the River Lérez comprises a lower deck arch with a span of 82,50 m and a rise of 13,40 m. Both deck and arch are steel structures. The arch is made up of a pipe of 1,00 m diameter. The deck which is 4,00 m wide and 0,80 m deep has a lens-shaped cross section.

The footbridge was built parallel to the river on one riverside. Once it was finished, the bridge ends were placed on two turning tables: one on shore and the other one off shore on a boat. The footbridge was first turned by the movement of the boat and then longitudinally shifted, holding the off shore bridge end with a crane and fixing the on shore one on a bed of sliding Teflon bearings which allowed its longitudinal launching.