web1_8973.jpg
Sants Station, Extension and Improvement Works . Above ground level
Barcelona. Spain
Date 2020-2023
Scope Preliminary project, detailed design and construction project
Cliente ADIF
Architect RCR Arquitectes
Owner Administrador de Infraestructuras Ferroviarias (Adif)
The work involved the reorganization and transformation of the Sants Station passenger building, as well as the plaza and the station"s surroundings (Joint Venture: RCR Arquitectes – Sener Ingeniería – Fhecor Ingenieros Consultores).

The main actions of the project include:

- Expanding the station on the Països Catalans side, allowing for the design of a new AV boarding hall on the Montaña-Països side (the expansion includes both ground-level and vertical growth).

- Creating a new access point for Cercanías (commuter rail) on the Mar-Països side.

The project was developed using BIM Methodology, with a BIM model at LOD 300.
Pro
The work involved the reorganization and transformation of the Sants Station passenger building, as well as the plaza and the station"s surroundings (Joint Venture: RCR Arquitectes – Sener Ingeniería – Fhecor Ingenieros Consultores).

The main actions of the project include:

- Expanding the station on the Països Catalans side, allowing for the design of a new AV boarding hall on the Montaña-Països side (the expansion includes both ground-level and vertical growth).
- Creating a new access point for Cercanías (commuter rail) on the Mar-Països side.

The project was developed using BIM Methodology, with a BIM model at LOD 300.
Sants Station, Extension and Improvement Works . Above ground level
Barcelona. Spain
Date December, 2023
Scope Preliminary project, detailed design and construction project
Cliente ADIF
Architect RCR Arquitectes
Owner Administrador de Infraestructuras Ferroviarias (Adif)
The work involved the reorganization and transformation of the Sants Station passenger building, as well as the plaza and the station"s surroundings (Joint Venture: RCR Arquitectes – Sener Ingeniería – Fhecor Ingenieros Consultores).

The main actions of the project include:

- Expanding the station on the Països Catalans side, allowing for the design of a new AV boarding hall on the Montaña-Països side (the expansion includes both ground-level and vertical growth).

- Creating a new access point for Cercanías (commuter rail) on the Mar-Països side.

The project was developed using BIM Methodology, with a BIM model at LOD 300.
location
Related projects