Combined cycle powerplant |
|
Túxpan de Rodríguez Cano, Veracruz, México |
|
|
|
|
Structural typology |
Industrial Structures |
Date |
December, 2020 |
Owner |
Iberdrola Energía Monterrey S.A. de C.V |
|
|
Construction Project of CC Tuxpan is located in the city of Tuxpan, Veracruz State, 6.55km far from the city centre.
It consists in the construction and operation of a Combined-cycle Power Plant with an energy generation power of 1228 MW. The Plant configuration is 2+1 (two gas turbine and one steam turbine).
The generation module consists of two gas turbines (with low NOx burning system), a steam turbine (with a final double flow body), two steam generators by heat recovery (HRSG) without post-burning, three electric generators and one air condenser.
FHECOR develops the engineering works (design and calculation) for gas turbine pedestals (Unit 1 and Unit 2), steam turbine pedestal and boiler stack (Unit 1 and Unit 2).