The interventions which took place have been on one hand the construction of a cantilevered service lane on the side of the bridge and on the other the operations of cleaning and structural rehabilitation.

These operations included the cleaning up and repair of the concrete facing and the subsequent application of anti-carbonation paint.

The arch masonrywork was repointed and then injected with grout for consolidation.

Improvements were made in drainage including spills, weep holes and sealing of joints between deck slabs.
Pro
The interventions which took place have been on one hand the construction of a cantilevered service lane on the side of the bridge and on the other the operations of cleaning and structural rehabilitation.

These operations included the cleaning up and repair of the concrete facing and the subsequent application of anti-carbonation paint.
The arch masonrywork was repointed and then injected with grout for consolidation.

Improvements were made in drainage including spills, weep holes and sealing of joints between deck slabs.
River Pisuerga Railway Bridge repair project
Villaescusa de las Torres, España
Typologie Rehabilitation Of Bridges
Date Juillet, 2012
Maîtrise d'ouvrage ADIF
Mission Extension and structural rehabilitation
The interventions which took place have been on one hand the construction of a cantilevered service lane on the side of the bridge and on the other the operations of cleaning and structural rehabilitation.

These operations included the cleaning up and repair of the concrete facing and the subsequent application of anti-carbonation paint.

The arch masonrywork was repointed and then injected with grout for consolidation.

Improvements were made in drainage including spills, weep holes and sealing of joints between deck slabs.